Startup draws on an existing furnace
Italian equipment supplier Danieli announced the first casting on November 2, 2026. According to SteelOrbis, Ramos II was ordered as DEACERO's fifth Danieli mini-mill.
For now, the new continuous caster receives steel from the existing electric arc furnace at Steelmaking Plant No. 1. Commissioning work is still underway on the new electric arc furnace at Steelmaking Plant No. 2, allowing the mill to start up gradually.
SteelOrbis reported that the equipment order specified a planned annual capacity of 1.5 million metric tons and the ability to make large sections up to 27 inches. The package includes a 150-metric-ton electric arc furnace with Danieli's "Zero-Man-Around" technology and an automatic system for feeding raw materials.
Investment and original projections
Cumulative investment in Ramos II has reached about $1.3 billion, according to SMM. The project was initially announced in June 2024 with an investment of $600 million.
In its June 5, 2024, statement, cited by Fastmarkets, DEACERO said the roughly $600 million plant would add 1 million metric tons of steel output to its existing production. At that time, the company projected a February 2026 production start.
DEACERO's original employment estimates called for approximately 1,000 specialized direct jobs and 2,500 indirect jobs, as well as up to 1,500 jobs daily during construction. Those figures were projections made when the project was presented in 2024, not confirmation of jobs already created.
Structural steel for domestic markets
Ramos II is intended to expand Mexico's steelmaking capacity and domestic supply, with an emphasis on large-dimension sections that can reduce reliance on imports. Planned products include beams and structural sections, followed by beam blanks for structural beams.
The mill will supply industrial construction, manufacturing and infrastructure projects. Fastmarkets, citing a DEACERO statement, reported that the structural profiles are also intended for the oil and gas industries and ship construction.
Fastmarkets places the Ramos Arizpe complex 182 miles from Laredo, Texas, which it describes as the main entry point for Mexican steel imports into the United States.
DEACERO produces about 4.5 million metric tons of steel products annually, including rebar and wire rod, according to Fastmarkets. Its production network also includes facilities in Saltillo, Coahuila, and near Celaya, Guanajuato.
Scrap-based production and environmental plans
The mini-mill uses recycled scrap in electric arc furnace steelmaking, alongside automation and digital tools. It forms part of DEACERO's green-steel strategy and its Neutrum range of reduced-carbon steel products.
DEACERO says its scrap-consuming electric arc furnace process has seven times fewer CO2 emissions than a blast furnace based on fossil energy. That comparison is the company's claim, as reported by Fastmarkets.
The company also plans to use treated water from Ramos Arizpe and Saltillo. Together with automated processes and digital controls, that measure is intended to reduce the environmental impact of operations.














